RALEIGH — The federal, North Carolina and Virginia governments asked a court Thursday to declare Duke Energy Corp. liable for environmental damage from a leak five years ago that left miles of a river shared by the two states coated in hazardous coal ash.

Government lawyers sought to have Charlotte-based Duke declared responsible for harming fish, birds, amphibians and the Dan River bottom.

Hazardous substances like arsenic and selenium poured into the river at levels high enough to harm aquatic life, according to a complaint filed in the North Carolina federal court district near the site of the 2014 disaster.

The leak of waste Duke Energy stored after burning coal for power coated about 70 miles of the river from a power plant near Eden, renewing national attention on the risks posed by similar storage pits across the country. Duke Energy pleaded guilty to federal environmental crimes in 2015 and agreed to pay $102 million.

The company said three years of testing through 2017 found no long-term effects to the river’s environment.

The government’s complaint “establishes beyond any doubt that the Dan River spill did serious harm,” said Frank Holleman, an attorney at the Southern Environmental Law Center. “The two states and the United States government are pursuing money and compensation for that harm.”

A tentative settlement also filed with the court for public review indicates the sides have agreed on the scope of the restoration needed.

Duke Energy already has paid to remove a defunct 1915 hydroelectric dam on the Pigg River in Virginia and added a boat dock and other improvements to a Danville, Virginia, park that was closed for months while coal ash was dredged from the river, the consent decree signed by the company and government officials said.

The power company also bought 340 acres in North Carolina and 214 acres in Virginia along the Mayo River, which was then transferred to state parks in both states. The restoration and plans for what remains left to do will be described in public meetings scheduled in the coming weeks, court documents said.

“These environmental projects conserve important land, improve aquatic habitat and allow more community access to nature and the outdoors,” said Paul Draovitch, a Duke Energy vice president for environment, health and safety. “We look forward to hearing the public’s feedback on this important work.”

Since the Dan River spill, Duke Energy has been prodded by court orders and a new state law to excavate coal-ash pits at eight of its 14 North Carolina power plants, with the ash to be stored away from waterways. But the company is fighting an order by state environmental regulators to also excavate its remaining six sites.

Duke had proposed covering some storage pits with a waterproof cap, saying that would prevent rain from passing through and carrying chemicals through the unlined bottoms and would provide a quicker and cheaper option.

Duke contends the expanded excavation requirement could double its costs to about $10 billion and take as long as 30 years to complete.

State utilities regulators last year allowed the company to begin charging ratepayers the first $778 million chunk of cleanup costs.

Virginia and South Carolina had already ordered its major electric utilities to remove all their coal ash out of unlined storage.

Charlotte-based Duke Energy has 7.6 million electricity customers in the Carolinas, Florida, Kentucky, Indiana and Ohio.

Comments

Coronavirus

Rowan County’s COVID-19 death toll tops 40 for September

College

Catawba-Wingate football game canceled

Crime

Blotter: Sept. 24

Coronavirus

Crowd turns out to raise money for hospitalized sheriff’s deputy

Coronavirus

COVID-19 death tally continues rising, now at 391 in Rowan County

Crime

‘No winners’: Mason found guilty in fish arcade murder trial

Local

Dixonville task force working to engrave names, quotes at cemetery

Coronavirus

Stage set for COVID-19 booster shots

News

Family finds unknown woman’s body in mother’s casket

Coronavirus

A third of workers in Cooper order not vaccinated

Nation/World

Remains of WWII soldier from North Carolina identified, will be buried in Robeson County

High School

State officials reach deal on prep sports governing, but details remain to be worked out

BREAKING NEWS

Mason found guilty in deadly fish arcade shooting

Crime

Blotter: Men stripped, robbed en route to buy beer

Crime

Jury begins deliberations in Fishzilla murder case

Education

East Rowan culinary students feed staff who helped build new classroom

Local Events

Rowan County Fair makes pandemic return Friday with COVID-19 protocols in place

Education

Education briefs: Schultz selected to NCDPI’s Teacher Leadership Council

Education

Catawba to induct six into Blue Masque Hall of Fame

Education

Cavs After Hours: A new tutoring space at North Rowan

Education

Shoutouts

Crime

Salisbury Police: Toyota Prius is most popular target for catalytic converter thieves

News

Salisbury City Council will vote on whether to exempt Goodwill developer from setback requirements

Local

Rowan Sheriff’s Office holding fundraiser for deputy hospitalized with COVID-19