Work begins on school system’s central office site
Published 12:15 am Tuesday, March 10, 2015
At long last, work has begun on the site of the Rowan-Salisbury School System’s future central office.
“I’m pleased with the way things have started,” Assistant Superintendent of Operations Anthony Vann said Monday. However, he added, “We’ve got a long way to go.”
Last week, crews installed the construction drive for construction vehicles and the silt fence.
The entrance is located on the Cemetery Street side of the property and is made of large rocks in order to remove the mud and dirt from the construction vehicles’ tires as they exit the property.
The silt fence is a low fence around the perimeter of the site with a black fiber material to keep the dirt from washing away during heavy rain.
“It keeps it on our property,” Vann said.
Crews began demolition of the Shulenberger house Monday.
“That house is on the ground now,” Vann said, adding that crews are working to remove the pieces from the site.
Crews are treating one of the other structures on the site for asbestos before demolishing it, as well.
Vann estimates it will take a week before that building is ready for demolition.
“As soon as all three structures are demolished and the site is cleaned up, we will start the earthwork,” he added.
Toward the end of next week, crews should be able to begin the earthwork on the site, which includes cutting, filling and shaving the site to make it level or balance it out.
The groundbreaking is scheduled for April 18 at 4 p.m. and will be open to the public.